SOPs

Procedure For line clearance activities during processing of product

STANDARD OPERATING PROCEDURE
Title:Procedure For line clearance activities during processing of product

 OBJECTIVE

To lay down the procedure for Line Clearance.

SCOPE

This procedure is applicable for line clearance activities during processing of product.

RESPONSIBILITY

Officer-Production

Officer-IPQA/QA

ACCOUNTABILITY

Manager-Production

Manager-Quality Assurance

PROCEDURE

Officer-Production should place the line clearance status board after ensuring the cleanliness and absence of foreign matters in area and request to Officer-QA.

On receipt of request from production for line clearance, Officer-QA should take the line clearance checklist as given in BMR/ BPR.

Officer-QA should check/ verify each and every activity as per format related to particular operation. Record the observation in the sheet and if found satisfactory, clear the line for next processing after putting his/ her signature in respective status board.

In case any deficiency related to any of the activity is found, he/ she should not clear the line for next processing and inform the Officer/ Manager-Production for remedial action.

Officer/ Manager-Production should rectify the deficiency and request again Officer for inspection.

Officer-QA should re-inspect the area/ machine, etc. for the deficiency noticed originally, if found okay, clear the line for processing.

If the deficiency is not yet rectified, he should not clear the line and ensure that next processing will not start without QA line clearance. Repeat the same as mentioned in above till deficiency is rectified.

General Procedure

Check general cleanliness of the area and equipments as per the attached format.

Ensure that previous batch is removed from the area and no excess Packaging/ Raw material is available in the area.

Check temperature, RH and differential pressure of the area if applicable.

Ensure availability of BMR/ BPR of the product to be manufactured/ Packed.

Dispensing

Check general cleanliness of the area and equipments as per the attached format.

Ensure availability of BMR of the product to be dispensed.

Check temperature, RH and differential pressure of the area and initial in sheet.

Ensure that the weight and weighing balance are calibrated.

Ensure that the Bulk is released from QC.

Ensure the ON / OFF position of LAF.

Put signature on line clearance status board.

Manufacturing

Check general cleanliness of the area and equipment as per the attached format.

Ensure availability of BMR of the product.

Ensure that the area is free from previous product.

Check temperature, RH and differential pressure of the area and initial in sheet.

Give the line clearance for the product to be packed by putting signature on the line clearance sheet in the BPR.

Filling

Check general cleanliness of the area and equipment as per the attached format.

Ensure availability of BMR of the product.

Ensure that the area is free from previous product.

Check temperature, RH and differential pressure of the area and initial in sheet.

Give the line clearance for the product to be packed by putting signature on the line clearance sheet in the BPR.

Polishing

Check general cleanliness of the area and equipments as per the attached format.

Ensure availability of BMR of the product.

Ensure that the area is free from previous product.

Visual Inspection

Check general cleanliness of the area and equipments as per the attached format.

Ensure that no other product is lying on the inspection bench except the product to be inspected.

Put signature on line clearance status board.

Blistering

Check general cleanliness of the area and equipments as per the attached format.

Ensure availability of BMR/BPR of the product.

Check all aluminum foils, PVC/PVDC foils, stereos of previous batch is removed from the area and no excess packaging material is available in the area.

Check temperature, RH and differential pressure of the area and initial in sheet.

Packing

Check general cleanliness of the area and equipments as per the attached format.

Ensure availability of BPR of the product to be packed.

Ensure that the labels, cartons, stereos, leaflets and finished product of previous product are not lying on the line.

Identify the product and check all packaging materials as per packaging material requisition slip.

Ensure the conveyor belt is clean.

Give the line clearance for the product to be packed by putting signature on the line clearance sheet in the BPR.

ABBREVIATIONS

SOP       –    Standard Operating Procedure

QA        –    Quality Assurance

FORMAT 

N/A

DISTRIBUTION LIST

Sr. No.Copy No.Department
Quality Assurance

 

ABHA

Abha is the Author  of pharmaceutical guidance, she is a pharmaceutical professional having more than 22 years of rich experience in pharmaceutical field. During her career, she works in the quality assurance department with multinational companies i.e Zydus Cadila Ltd, Unichem Laboratories Ltd, Indoco remedies Ltd. During his experience, she faces many regulatorily audits i.e. USFDA, MHRA, ANVISA, MCC, TGA, EU –GMP, WHO –Geneva, ISO 9001-2008 and many ROW Regularities Audit i.e.Uganda, Kenya, Tanzania, Zimbabwe. She is currently leading a regulatory pharmaceutical company as a Head Quality. You can join him by Email, Facebook, Google+, Twitter, and YouTube